Date: November 6, 2025
Project: NEAR Integration
Current Status
- SDK development nearing completion, expected by mid-November.
- External audits scheduled to begin on November 11.
Integration Status
- Only pending item is solver integration into one of NEAR’s AMMs.
- Mainnet deployment planned after audits and solver integration are finalized.
Dependencies
- Completion of SDK component.
- Successful execution and review of external audits.
- Solver integration into target AMM.
Next Steps
- Finalize SDK development.
- Begin and complete external audits on November 11, then apply required fixes.
- Proceed with solver integration.
- Target mainnet deployment by mid-December.
Date: October 17, 2025